The Madelia City Council approved an updated quote of $164,145 to replace library windows, with staff saying casement windows will be more efficient and secure than the originally coded sliders; the rental building work was approved at $7,339.50.
Get email alerts on the Capital Project Library Windows topic
No spam. Unsubscribe anytime.
At its April 25 meeting the Madelia City Council approved an updated quote to replace windows at the public library and an associated rental building.
Staff member Matt told the council that, on review, many windows initially coded as sliders would instead be installed as picture or casement windows. "The sliders aren't going to last. They're a weaker window, less secure," Matt said, explaining the change in specification to casements for better efficiency and security. The library work was quoted at $164,145; the rental-building portion was $7,339.50.
Council members discussed the procurement history: staff reported only one responsive bid was received (a second expected bidder, Schmidt, did not submit a proposal) and the city had delayed action pending additional bids. With no additional responsive offers, council approved the single responsive quote by voice vote.
The council recorded no roll-call tallies in the transcript; staff were directed to proceed with the replacement. The quotation and single-bid circumstance may prompt follow-up on competitive procurement and vendor outreach in subsequent meetings.