Summary
Public Works Director Roger Nowell told the authority that property and easement agreements for Antrim Well 3 were sent for solicitor review, CoStars contractors were sent bid packages on Feb. 13, bids are due March 13, and a public bid opening and an Oct. 2026 completion target were announced.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
Public Works Director Roger Nowell updated the Antrim Township Municipal Authority on ATMA Well No. 3 at the Feb. 23 meeting, saying property and easement agreements have been prepared and were sent to a solicitor for review.
Nowell said CoStars contractors received bid packages on Feb. 13 and that bids are due March 13, 2026; he said a public bid opening will be held and that the suggested project completion date is October 2026. He also said easement and access agreements for the Exit 3 public water extension have been sent to Bowman and staff are responding to questions.
The minutes reference Solicitor Linus Fenicle in attendance earlier in the meeting but refer to a 'Solicitor Lisko' in the Well 3 update; the minutes contain that name variance and do not explain it. The board did not take a final procurement vote at the meeting; the next procedural milestones are the March 13 bid deadline and any subsequent public bid opening.