Hoyt Lakes council approves arena change orders; contractors finish punch list items

Hoyt Lakes City Council · December 22, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The council approved Change Order No. 5 and Pay Application No. 15 for the new arena project; staff said the work addressed a missed locker-room door, upgraded lighting circuits and structural steel for bleachers and that remaining punch-list items are small.

Hoyt Lakes city officials approved Change Order No. 5 and Pay Application No. 15 for the city arena project during the Dec. 22 meeting.

Recreation Director Peterson told the council crews removed older equipment from the compressor room, added a heater and reworked lighting circuitry to reduce frequent breaker failures. Peterson said crews have completed much of the punch list and the arena is close to full operation.

Project lead Bucky described Change Order No. 5 as covering a previously-missed locker-room door, additional structural steel associated with new bleachers and work required to accommodate an elevator and recessed wheelchair ramp. Bucky said some contractor markups were waived or reduced, which saved the city money on the change order. The council approved the change order and Pay Application No. 15 (recorded as $122.40) by voice vote.

Staff reported there remains contingency funding and that these items should finish the outstanding work once installed and inspected.

Next steps: staff will continue punch-list walk-throughs and confirm final payments when work is complete.