Council approves $44,253 lift‑station rehab after emergency pump failures
Summary
Following a major pump failure at Lift Station No. 1, the council authorized purchasing a full rehab quoted at $44,253 to replace failing pumps and avoid repeated emergency mobilizations; temporary pumps are in place while the work is scheduled.
Get email alerts on the Utilities Repairs topic
No spam. Unsubscribe anytime.
Public Utilities Director Bend told the council the city experienced a significant failure at the Atlas lift station when two pumps failed and the remaining system risked overflow. Bend said crews "had to call state duty offices" and that emergency contractors supplied temporary pumps to keep the system functioning.
Bend reviewed the written quote from Quality Flow and explained rebuilding the existing pumps and guide rails on a single callout would cost $44,253; staged work requiring multiple mobilizations would increase total cost. "If we have the funds for it and it's something that we need and it'll be kind of a cost saver, we just do it now rather than kicking it down the road," a councilor said in discussion.
Councilors approved the purchase of the full rehab to reduce the risk of repeated emergency responses and longer‑term expense. Staff said funds are available in the infrastructure budget but noted doing the work now slightly increases risk to other contingency balances if additional main breaks occur before year‑end.
The purchase was approved and Quality Flow will be scheduled to perform the rebuild; temporary pumps will remain in place until the contractor completes the rehab.