WPCA reports operations updates; Woodard & Curran to provide bidding-phase scope for Stony Brook project

Suffield Water Pollution Control Authority & Treatment Facility · May 12, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Superintendent Jamie Kreller reported operational work (pump upgrade, fence repairs, rigging) and that the WPCA is 91 dry tons below its annual solids-disposal allotment; consultant Woodard & Curran will provide a bidding-phase scope for the Stony Brook project while revising construction-phase services.

Superintendent Jamie Kreller reviewed routine operational activity at the Suffield Water Pollution Control Authority's May 12 meeting, reporting equipment work and maintenance and noting the authority is currently 91 dry tons below the yearly solids-disposal allotment under the MDC agreement.

Kreller said a new variable-frequency drive (VFD) was installed for pump 1 at PS 1 (Thompsonville Road), operators completed repairs to fencing and concrete supports at PS 13 (Stony Brook Drive), and rigging and a winch were set up at the PS 1 dry well to improve emergency maintenance access for a new pump. Kreller and Anna Clark presented the WPCA budget to the Board of Finance, which included discussion of potential future review of prison and commercial sewer rates and of Lake Congamond sewer service boundaries.

Patrick Compton, Woodard & Curran representative, reported the firm had developed a proposal for construction-phase services on the Stony Brook project. The commission asked Woodard & Curran to evaluate opportunities to reduce the fee and agreed the firm would provide a bidding-phase scope of services only to help maintain the project schedule while it revises the construction-phase proposal.

The minutes record no operational issues with DEEP or EPA reporting; quarterly reports were completed successfully with no issues noted.