Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Local Infrastructure topic

No spam. Unsubscribe anytime.

Council reviews sports-complex payment and opens public hearing on chemical feed building for Well #5

Lisbon City Council · August 11, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The council considered payment number three on the sports-complex grading contract (retention $28,440; project ~78% complete) and opened a public hearing on construction of a chemical feed building at Well #5, which staff said is supported by a Lynn County grant (recorded as $1 million) and has an estimated additional cost of about $750,000 for the building phase.

The Lisbon City Council considered two infrastructure items: a contractor payment related to the sports complex and a public hearing on construction of a chemical feed building for Well #5.

Payment for sports-complex grading: Staff presented payment number three to Lin Haven Land for the sports-complex grading work. After staff reported the project was roughly 78% complete and described remaining items (seed and silver removal), a council member moved to approve the payment and a second was recorded; a voice vote was called but no roll-call tally appears in the meeting record. The payment amount net of retention was given on the record as $28,440.

Public hearing opened on chemical feed building: The council then opened a public hearing on "Building Number Five," a chemical feed facility at the northwest corner of the outdoor sports complex (Jefferson and Third). Staff described the project as a chlorine feed and storage building that can be expanded later to add filtration if needed. Staff said the town drilled and tested a new well after leased wells were closed, and that the new building will provide redundancy so the system can meet peak demand.

Funding and costs: Staff reported a county grant described during the hearing as "art funds" of $1 million toward the broader project. For the current work, staff said the estimated construction cost is about $750,000; the town previously spent about $300,000 on drilling and testing the well. Bids are out; an addendum in the bid package moved the bid date back by about a week to allow contractors more time.

Next steps: Staff said they will review bids when received and report back with final numbers. The public-hearing format was used to allow residents to ask questions; no final construction contract award or formal appropriation was recorded during the meeting.

Other infrastructure updates: The city administrator reported that the sports-complex gravel overflow lot is complete, TIF documents were finalized with the auditor, street work is planned for late August, and the recently completed water-main project produced an estimated in-house savings of $70,000–$90,000 on asphalt work. The police chief outlined event safety operations for Sauerkraut Days, including street washing and Saturday's bathtub races.