Board funds $25,000 study for Waterford police station HVAC; roof repairs remain separately funded
Summary
The Board of Finance approved $25,000 to study and design the police department HVAC system; members clarified the town earmarked $85,000 separately for roof repairs and discussed a one‑ to two‑year project timetable.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
The Waterford Board of Finance approved $25,000 on Thursday to fund study and design work for the police department’s HVAC system.
Director of Public Works Gary Schneider told the board the request—an appropriation move from a designated line (20511‑57871)—covers engineering and planning for chillers, boilers, valves, blowers, variable‑air‑volume boxes and a building management system. Schneider said the town will meet with the police chief to identify user needs before finalizing design requirements.
Board members pressed whether roof work was included. Schneider said the roof repair is a separate item: the town has an $85,000 earmark for a portion of the police station roof; the $25,000 is specifically for HVAC planning and will produce a high‑level cost estimate. Members discussed timeframes; Schneider said the study could be completed within roughly six months but the overall project could run a year or up to two years depending on design and procurement.
The appropriation was moved, seconded and approved by voice vote; the item will be forwarded to the Representative Town Meeting for final authorization and subsequent steps for engineering procurement.
Next steps include engaging an engineer to perform a needs assessment with police staff and deliver a preliminary cost estimate for board review.