Corydon council approves skate-park fencing and repairs using contingency funds

Corydon Town Council · April 21, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Corydon Town Council approved immediate safety upgrades to the skate park, including concrete repairs and a perimeter fence; staff presented line-item estimates and said an existing $50,000 contingency in the contract could cover most costs.

The Corydon Town Council on Monday voted to move forward with safety improvements and fencing at the town skate park, approving staff recommendations that pair concrete repairs with a new perimeter fence.

Council members heard a line-by-line estimate from staff: Midwestern was quoted a not-to-exceed $5,000 special-fees allowance, the fence and concrete work were listed at about $15,700, and asphalt curbing and related site work at roughly $35,000. The project also includes a $50,000 contingency in the contract that staff said remains unspent and can be used to offset the added costs.

Why it matters: Town officials described the work as a safety priority to address cracked concrete and “dead spots” in the park surface and to reduce risks for users. Staff recommended proceeding now to avoid higher costs later and to complete work while other park improvements are under way.

Council recorded a motion and voice vote to approve the work. Staff told the council the minimum additional cost could be about $5,700 depending on final line-item allocations and any INDOT requirements for right-of-way or hydraulic analysis.

Town staff will finalize procurement and scheduling; council members asked staff to provide final contract amounts and a timeline once negotiations with vendors conclude.