Highway Superintendent Joe Miller presented a 2027 plan emphasizing one-time capital purchases (motorgrader blades, vacuum broom), $5.6M in bridge grants enabled by the wheel tax, a proposed 50/50 drainage basin design cost-share with Rapid City and a multi‑vendor evaluation of asset-management software (PubWorks / Omnitech / Tyler) estimated at $350K–$400K for a custom in‑house solution.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
Joe Miller, superintendent of the Pennington County Highway Department, briefed the commission on FY2027 highway priorities and a review of the department's software needs.
Miller said operating expenditures were kept flat while one‑time capital outlays account for the budget increase (about 5%). The department plans routine equipment replacements for motorgrader blades and pickup trucks, and noted purchases this year included a mastic patching machine and a used paving machine acquired for $2,500 to pilot in‑house paving. Miller reported $5.6 million in bridge funding secured through a combination the county called "the big grant," tied to the wheel tax; total bridge project costs are estimated at about $8.9 million if done in-house.
On drainage, Miller said the county and Rapid City intend to split the design cost for a drainage basin between Reservoir and Radar Hill 50/50; the estimated design cost is $250,000–$350,000 and would draw from county drainage reserves.
Miller also described a multi‑year software dilemma: the highway department currently uses PubWorks (now owned by GWorks) for asset tracking and GASBY‑34 reporting, but staff explored building a custom in‑house solution with Omnitech at an estimated $350K–$400K or adopting Tyler modules at much higher license and implementation costs. Commissioners requested a full presentation comparing costs, integrations with Tyler financial systems, and long-term support models before any commitment.
Commissioners and staff also discussed fleet management, vehicle insurance and a county‑wide fleet inventory project being coordinated with SDPAA and other departments.