Town says pipelines complete and grading permits received for new Hampstead water treatment plants

Hampstead Planning and Zoning Commission · June 24, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Town staff reported pipelines for the new water system are installed and flushed; grading permits for four water treatment plant sites were received from Carroll County and grading may start soon, with overall completion estimated in July–August 2027.

At the June 24 meeting the Zoning Administrator updated the commission on the town’s water system projects, reporting that pipelines for the new water distribution system are installed and have been flushed to prevent long-term standing water.

"All the pipelines are done now. They actually came in yesterday. There was water laying in the pipes ... so, they'll still have to ... be treated when they're brought back into service, but at least there's not going to be water sitting in there for 9 months," the Zoning Administrator said.

On the water treatment plant side, staff said they held a pre-construction meeting with Carroll County grading and sediment control and received the final grading permits for all four planned treatment plant locations. "Carroll County can now begin the grading," staff said, and they expect to see dirt moving by the next monthly meeting. The Zoning Administrator reiterated the contractor schedule remains on track for completion in July or August of next year.

No formal vote or further action was taken; the report was informational and staff will return with progress updates at future meetings.