Winfield Sewer Board approves final payments to Hassing Construction and declares expansion complete

Winfield Township Sewer Board · June 23, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Winfield Township Sewer Board approved two final payments to Hassing Construction — a $26,063.96 change-order payout and a $26,063.96 final pay application — and accepted completion of the wastewater plant expansion, which staff said increases capacity to 1.6 million gallons per day.

The Winfield Township Sewer Board voted to approve final payments to Hassing Construction and sign off on the town—s wastewater plant expansion, board members said.

A committee member moved "I'd like to make a motion to pay Hassing Construction the amount of $26,063.96 for order number 10," and another member seconded; the board responded "Aye" and the motion carried. The board later approved pay application number 21, described in the meeting as the final pay application, for the same amount by a similar motion and vote.

Chair said the board had reached the last payouts for the project and noted punch-list work on clarifier one was finished. "I want to commend the board for sticking with this project. It was a big one," the chair said, praising board members for overseeing the work and specifically referencing Mark Watnick—s familiarity with wastewater expansions.

Staff said the completed expansion raises plant capacity to 1.6 million gallons per day, a change they said will position the town for future development without immediate additional projects.

Votes at a glance

- Motion to approve minutes from the May 26, 2026 meeting: carried (aye). - Change order #10: motion to pay Hassing Construction $26,063.96; carried. - Pay application #21 (final pay): motion to pay Hassing Construction $26,063.96; carried.

The board did not record any dissenting votes in the transcript. The meeting set a date for the next regular session and then adjourned.