Eveleth Awards Sidewalk Contract, Approves Utility Change Order and Arch Demolition
Summary
Council awarded a 2026 curb-and-sidewalk contract to the low bidder (3D Concrete), authorized change order 24 for corridor utility work (about $50,260.23, grant-funded), and approved the lower bid to remove a deteriorated downtown arch, with steps to protect adjacent businesses.
Get email alerts on the Infrastructure Contracts topic
No spam. Unsubscribe anytime.
The Eveleth City Council on April 20 approved several infrastructure actions: awarding the 2026 curb-and-sidewalk replacement contract to 3D Concrete, authorizing change order 24 on a multi-million-dollar corridor utility project and accepting a low bid to remove a deteriorating downtown arch.
Jerry presented two bids for curb and sidewalk work and said the city is contributing $30,000 while the county is contributing another $15,000 for certain routes; staff recommended 3D Concrete as the lower bidder and the council approved the award. ‘‘3D concrete came in with the lower prices. So, I am recommending 3D get this again this year,’’ Jerry said.
On the large corridor project, staff reported that ledge rock and an unexpected culvert were encountered and that the city added a valve to limit water disruption to nearby businesses. Alan summarized the utility portion of a $22 million investment and said the change order attributable to the city was approximately $50,260.23, funded by grant sources for the project; the council authorized the change order.
For downtown, staff presented two demolition proposals to remove a deteriorating arch structure adjacent to businesses. Council approved the lower bid and discussed protections for the adjacent chiropractor and bar during a brief closure; staff said the contractor is insured and will coordinate with police to close that block only as needed.
All approvals were made by voice vote; staff will coordinate scheduling, street-closure notices and business outreach before any work begins.