Cokato delays street relining as costs rise; council approves partial payment for holding pond
Summary
City staff reported rising costs and a roughly one-year delay for planned street relining; the council approved partial payment #3 for the Southwest Holding Pond project (project ~95% complete) and reviewed a GIS cost comparison between Bolton & Menk and Silversmith.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
Cokato city staff told the City Council on Oct. 14 that rising costs have pushed planned street relining work out roughly a year.
City Administrator Brad Potter and contractor representative DeGrote reviewed a list of streets needing repair and said relining costs have increased; staff described the earliest feasible start as about a year away. Potter also presented a cost spreadsheet comparing proposals from Bolton & Menk and Silversmith for a city GIS system; no procurement decision was recorded at the meeting.
On capital work, staff recommended and the council approved partial payment #3 for the Southwest Holding Pond project; staff reported the pond is about 95% complete. Council Member Wilson moved to approve the payment, Council Member Hermansen seconded, and the motion passed unanimously.
No additional funding or contract amendments were recorded in the minutes; further scheduling and procurement actions will be handled by public-works staff.