Council briefed on $929,000 amendment to advance downtown flood-mitigation final design and lift‑station work

Burlington City Council Meeting · February 23, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff recommended amending the HR Green professional services agreement to move flood-mitigation design from 30% to final plan/bid documents. The $929,000 amendment covers design for extended flood walls, inlet sealing near the auditorium and storm-water lift stations to pump over the wall; funding is expected from the sales-tax increment/flood-mitigation revenue.

City staff presented amendment No. 1 to the HR Green professional services agreement at the Feb. 23 work session to advance flood-mitigation work downtown from 30% design to final design and bidding documents.

Mr. McGregor described the scope: extend permanent and temporary flood walls down Market Street toward Main, design a sealing solution for storm inlets beneath the auditorium to eliminate temporary defenses (hesco baskets), and design storm-water lift stations with valved alternate storm lines to route rainwater to pumps that would discharge over the wall during high-river events. He told council that the most complex and costly element is the lift-station work and that wet-weather pump capacity and new storm-line routing will require careful construction where existing utilities converge.

The contract amendment was presented with a total estimated design cost of $929,000. Mr. McGregor said the flood-mitigation revenue stream and associated sales-tax increment would be the primary funding source for this phase of work.

Why it matters: The amendment would move critical design work forward for downtown flood protection, reduce reliance on temporary protective measures at key facilities and identify construction-level details around storm piping and pump capacity. The work will require coordination with other utilities and minimize disruption at recently paved intersections where possible.

Next steps: Council was asked to consider the resolution as part of the next regular agenda; staff will bring the amendment forward for formal action. The design will inform final cost estimates and subsequent construction bidding.