City approves $519,910.77 payment to Boomerang Corp. as wastewater project nears completion

West Branch City Council · June 1, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The West Branch City Council approved Pay Estimate No. 17 for $519,910.77 to Boomerang Corp. for Wastewater Treatment Facility improvements; city engineer said the project is roughly 90% complete and commissioning and final grading remain.

The West Branch City Council on April 15 authorized Pay Estimate Number 17 in the amount of $519,910.77 to Boomerang Corp. for work on the Wastewater Treatment Facility Improvements Project.

City Engineer Dave Schechinger told the Council the project is roughly 90% complete, explaining that final grading and bringing the facility online would finish the remaining work. The Council approved Resolution 2024-33 to release the payment.

Councilmembers noted progress toward completing the facility and moved the project toward final commissioning and closeout.