Mayor outlines amphitheater timeline; staff report on test kitchen, Westgate delays and wastewater staffing

Columbia City Common Council · June 23, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City leaders told the council that amphitheater drawings should be 90% complete by July 22, triggering GMP-related steps; staff also reported on a proposed test kitchen, Oki Alley work, a Westgate utility delay tied to NIPCO, and wastewater staffing changes.

During reports to the Columbia City Common Council on June 23, the mayor and staff provided several near-term project and operations updates that city leaders said will shape procurement and construction work in the coming weeks.

The mayor reported that the amphitheater’s acoustical review is underway and that staff expect drawings to reach 90% completion by July 22. "We're looking at July 22nd being 90% done with the drawings which... should start to trigger the GMP guaranteed maximum price area so we can have that around by August," the mayor said, linking the drawing milestone to the timeline for guaranteed maximum price discussions and subsequent contracting steps.

City staff described several capital and neighborhood projects: a bottle-fill water station, drinking fountain and dog bowl were installed at Eagle Park; plans are underway to remodel the north end of Oki Alley, including removing existing trellises and installing trees and new plantings. The mayor said he requested a CIP committee meeting on July 14 to consider remodeling a space into a test kitchen with appropriate equipment.

Staff also reported a delay on the Westgate development: NIPCO has relocated a gas line but could not provide a firm completion date, estimating two to three weeks before certainty. In wastewater operations, the long-time wastewater supervisor Bob was reported retired and staff said Brian has been appointed the new wastewater supervisor; staff rented four samplers to continue monitoring ammonia levels at multiple locations to confirm remediation work is effective.

Parks and events updates included a near-complete dog park (waiting on replacement locks from a vendor), preparations for July 3 fireworks and a July 4 time-capsule opening at 1 p.m., and continued low pool attendance attributed to cool, rainy weather.

What’s next: staff will pursue the stated project milestones, convene the CIP committee for the test-kitchen proposal on July 14, and continue operational monitoring of wastewater ammonia with the rented samplers.

Quotes - Mayor on the amphitheater timeline: "We're looking at July 22nd being 90% done with the drawings... which should start to trigger the GMP guaranteed maximum price area." (attributed to Mayor)