Board approves Measure C construction GMPs for Bishop’s Peak and Del Mar projects

San Luis Coastal Unified Board of Education · June 16, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Trustees approved lease‑leaseback sublease amendments setting GMPs for Bishop’s Peak (new 12‑classroom building; GMP $9,757,097.82 excluding contingency) and Del Mar Phase 2 modular/demolition work (GMP $2,561,502), with staff noting ongoing summer demolition and construction sequencing.

The San Luis Coastal Unified Board of Education on June 10 approved guaranteed maximum prices and related lease‑leaseback sublease amendments for two Measure C projects: Bishop’s Peak Elementary Phase 2 and the Del Mar Elementary Phase 2 modular/demolition work.

For Bishop’s Peak, staff said the work this summer will demolish two classroom buildings and replace them with a 12‑classroom stick‑built building constructed by RSH Contractors. The staff presentation described the GMP (excluding allowances and contingency) at $9,757,097.82; demolition is scheduled to occur over the summer with the goal that the site be ready to start construction when school resumes. Trustees approved the GMP by a 6‑0 vote.

For Del Mar Elementary, staff described moving three portables for temporary housing, demolishing an existing child‑care room and older portables, constructing a retaining wall and preparing utility and playground work for phase two. The GMP presented (excluding contingency) for the Del Mar modular and site work was $2,561,502. Trustees approved the sublease amendment setting that GMP 6‑0.

Staff emphasized coordination with site administrators to maintain summer school and other on‑site activities during demolition and construction; temporary classrooms will be placed as needed and work sequencing is planned to minimize disruption.

Both approvals were described as part of the district’s ongoing Measure C implementation across 94 projects and are funded by bond proceeds. The board’s motion carried unanimously for both items.

Next steps: staff will manage construction schedules, process payments in the established schedule, and report progress to the board as the projects advance through DSA approvals and into active construction.