Staff outlines $228,000 change order for Chester public works building tied to subsurface finds

Chester City Council · June 22, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff reported a not-to-exceed $228,000 change order for the public works building to remove an underground storage tank, contaminated soil, a deep concrete slab and unsuitable soils; staff said contingency funds will cover the cost and the project remains on track for mid-November completion.

City staff presented change order No. 4 for the Chester public works building on June 22, citing unexpected subsurface conditions that have increased costs by about $228,000.

Staff said crews uncovered an underground storage tank and contaminated soil, together costing roughly $88,000 to remove and dispose of. Excavation revealed a deep subgrade concrete slab beneath the planned salt shed location that required removal (about $21,000). Staff described additional unsuitable soils that could not be compacted or reused; they estimated a not-to-exceed $120,000 to remove and replace those soils. Taken together, staff framed the total change order at approximately $228,000 and said the work will be paid from the project's contingency line.

Project staff told the council they still expect to complete the building by mid-November and that this change order reflects subsurface conditions typical of brownfield sites. The transcript does not include a public roll-call vote; staff indicated the contingency budget will cover the work and anticipated this would be the bulk of remaining subsurface change orders.