Jay County approves financial commitment for Bridge #64 federal funding application
Summary
The Jay County Commissioners approved a financial commitment letter to pursue federal funding for Bridge #64 on 400 N, agreeing to local matching obligations estimated at about $394,000 of a projected $1.97 million construction cost and to preliminary engineering estimated at $301,000.
Get email alerts on the Infrastructure Bridge Funding topic
No spam. Unsubscribe anytime.
The Jay County Commissioners voted unanimously Nov. 10 to approve a financial commitment letter supporting a federal funding application for Bridge #64 on 400 N.
Stephanie Klarer, assistant superintendent/ERC, told the commissioners the preliminary engineering is estimated at $301,000, with 80% expected to be reimbursed. She said about $100,000 of right-of-way work is estimated in 2028 (80% reimbursed), utility relocations are scheduled for 2030, and construction is estimated in 2031 at roughly $1.97 million, of which the county’s share would be approximately $394,000. Klarer said Bridge #64 was the last locally scored bridge with a rating of 4 or under that qualified for the federal funding program.
The board approved the financial commitment letter by unanimous vote after Doug Horn moved for approval and Chad Aker seconded.
Why this matters: the federal program would cover the majority of project costs but requires the county to certify its intent to provide the local match and to proceed through preliminary engineering and right-of-way work. The application deadline for the federal funding was reported as Dec. 1, 2025.
Next steps: county staff will proceed with the application and preliminary engineering work in advance of the funding deadline.