After opening eight bids for the Holiday Street sanitary sewer improvements, staff identified Chambers Excavating as the apparent low bidder but recommended waiting for a signed easement from the Winters property; council scheduled a short special meeting on April 15 to decide the award if the easement arrives.
Get email alerts on the Procurement topic
No spam. Unsubscribe anytime.
City staff reported that Good Thunder received eight bids for the Holiday Street backyard sanitary sewer improvements and identified Chambers Excavating as the apparent low bidder. Staff said they were reluctant to recommend awarding the contract until a signed easement from the Winters property is in hand; the bid bond for the apparent low bidder expires June 4, 2024.
Council members discussed timing and agreed that a short special meeting could be scheduled to award the project as soon as the easement is returned. A motion to hold a special meeting on April 15 at 4:30 p.m. to consider a resolution awarding the project to Chambers passed unanimously. Staff said final award recommendations will include confirmation that the contractor can meet schedule and permit requirements and that the easement is signed prior to an award.