Gaylord council lays groundwork for citywide sewer televising program to find illicit connections

Gaylord City Council · July 17, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council discussed a planned inflow-and-infiltration (I&I) program to televise sewer mains and laterals, preliminary per-block cost estimates, enforcement timelines and possible city cost-share for homeowner repairs; staff will return with budget estimates and a recommended ordinance and workshop schedule.

City of Gaylord staff briefed the council on a proposed inflow-and-infiltration (I&I) program intended to reduce basement backups by identifying illicit connections and failing laterals.

Staff said televising mains to inspect laterals and service lines is a proven way to document I&I. Preliminary figures presented to the council included an average of about $1 per foot to clean a mainline ahead of televising and sample televise service costs in the transcript that produced an illustrative per-block estimate in the range of roughly $2,750 to $3,300 depending on the number of houses on a block. Staff cautioned these figures are preliminary and will be refined in a budget estimate.

Council and staff discussed equipment versus contractor models. Staff noted that push-camera reels used by plumbers are inexpensive but not suitable for mainline televising; contractor systems that launch lateral cameras from a mainline (described in the meeting as a wheeled “robot” with recording and documentation software) are substantially more capable and more expensive. The presentation referenced vendor price ranges discussed by staff during the briefing; staff recommended pursuing contractor services for citywide work while evaluating whether limited city-owned capability would be cost-effective for targeted needs.

A second set of decisions discussed was how the city would respond when inspections identify illicit or failing connections. Staff outlined options for ordinance language that would set a compliance timeline (examples discussed included 12to18 months) and described models used in other communities in which the city contributes a capped cost-share toward homeowner repairs and records the arrangement in a written agreement with the homeowner.

Councilmembers and staff agreed on program phases and sequencing: create a block-by-block map, prioritize areas with recurring flooding, and establish an expected completion schedule so residents can see when their neighborhood will be inspected. Staff estimated roughly 100 blocks as a high-level planning figure and said the first year would likely be a learning year to refine repair rates and costs. Councilmembers said they would consider a multi‑year rollout (three to five years was discussed) but some members expressed willingness to accelerate work if funding allows.

Next steps: staff will develop budget options and draft ordinance language, then convene a dedicated work session for council to review costs, timelines, enforcement mechanics and potential cost-share terms before returning to a formal council agenda for any policy or budget action.

"We could set this up almost like a street-improvement project map where people could see when their block or their neighborhood would be completed," staff told the council during the briefing. The council did not take a formal vote on the program itself at this meeting.