City staff reviewed the draft FY26 Capital Improvement Program, recommending near‑term work on bridge and intersection projects, sanitary lining as an annual program, and flagging a $4 million placeholder for library expansion; council discussed federal funding constraints for an Eagle View water‑main extension and options to phase projects.
Get email alerts on the Capital Budget topic
No spam. Unsubscribe anytime.
City staff presented a draft FY26 Capital Improvement Program (CIP) and previewed budget considerations that will be discussed in detail at a scheduled special budget meeting.
Shane and other staff walked council through a multi‑page CIP. Key items included West Cemetery Road bridge and intersection projects recommended for one‑year funding, an Eagle View water‑main extension that staff recommended postponing or reclassifying because of federal SRF environmental‑review complexities, and a sanitary‑rehab program proposed as an annual work item funded at roughly $150,000–$200,000 per year or pursued as larger multi‑year packages.
Staff placed a $4 million placeholder for a library expansion on the five‑year list, noting the $4 million figure was a planning estimate that could change with design fees, land acquisition or inflation. "I put $4 million in there for that item," staff said when describing the five‑year CIP placeholder for library expansion. Council asked for the most recent CIP files to be distributed before the next meeting so members could review updated figures.
On the Eagle View water‑main extension, staff noted federal funding rules and environmental review requirements mean the project may need to be staged or moved to a longer planning horizon; council discussed whether to include the extension in the one‑year or five‑year CIP or combine it with other projects.
Staff asked council to review the CIP prior to a special budget meeting and to email questions so department staff have time to prepare detailed answers. A special budget meeting was scheduled for January 28 to refine levy and payroll assumptions and to finalize budget directions ahead of deadline notifications to the county tax office.