Staff reported base failures discovered in first‑round paving on 10th–14th streets and elsewhere, said contractor Ruth Riley is preparing repair pricing, and the redevelopment commission voted to hold a special meeting Wednesday to allow prompt authorization of repairs once bids arrive.

Town staff told the Redevelopment Commission that milling and initial paving work uncovered significant subgrade/base failures in parts of the town (notably 10th–14th streets and the TIF district) caused in part by heavy truck traffic and previous road cuts. The contractor, identified in the meeting as Ruth Riley, is preparing repair cost estimates for options such as cement re‑stabilization or full removal and replacement with compacted stone.

A staff member said the town would prefer to repair base failures before final paving to avoid rapid deterioration. "We have found a significant amount of base issues...the trucks are actually showing and leaving imperfections in the road base that need to be repaired before we can go further," the staff member said. The contractor was asked to provide prices; staff anticipated receiving estimates the following morning and urged commissioners that quick action might be needed to avoid further delays.

Because legal notice rules require at least 48 hours' notice for special meetings, commissioners discussed scheduling constraints; the commission ultimately moved and approved a special meeting on Wednesday at 7:15 p.m. by voice vote to consider urgent paving repair authorization if needed.

Ending

Staff will return with repair pricing and, if necessary, the commission will consider authorization at the special meeting. No expenditure was approved at the regular meeting.