District sets $5.3 million estimate for 38th Place project; bids to run with County Line culvert work

Hoover Sanitary Stormwater District · March 24, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff presented plans and permits for 38th Place/Fillmore Phase 1-2, estimated at about $5.3 million (15% contingency). The board authorized bid advertisement and directed concurrent bidding of the County Line culvert project to align procurement schedules.

The Hoover Sanitary Stormwater District authorized staff to advertise bids for Phase 1 and 2 of the 38th Place/Fillmore stormwater improvements and agreed to reissue County Line culvert bid documents to run concurrently.

Staff said DNR permits for the Stacey Creek outfall have been received, specifications and plans are complete and a mandatory (or optional, per item) pre-bid is scheduled for April 30 with bids to be opened May 7 and an award targeted for the May 12 meeting. Staff estimated Phase 1 and 2 construction at about $5.3 million including a 15% contingency.

Board members discussed combining projects in the same procurement window to improve contractor turnout and pricing; staff recommended separate bid packages run at the same time to preserve scope clarity while leveraging concurrent advertising. The board approved moving forward with the 38th Place bid and concurrently reissuing the County Line culvert procurement.

Staff noted Phase 3 (additional culvert through the railroad) remains preliminary and will be budgeted in a later phase. The procurement schedule and estimated budget were recorded for future award consideration.