Summary
Mayor Parsons said contractors will return Thursday to complete fog/chip seal work on several streets and estimated one to two weeks to finish the FY26 paving program; staff explained fog/chip seal is meant to extend life of 'fair' roads and that the city uses a Pavement Condition Index and Pavement Management Group for evaluation.
Get email alerts on the Transportation Paving topic
No spam. Unsubscribe anytime.
At the June 23 Board of Mayor and Aldermen meeting, city officials provided a detailed update on Bartlett’s FY26 paving preservation plan and explained why certain streets are receiving fog/chip seal rather than full milling and repaving.
Mayor Parsons told the board the contractor is scheduled to return Thursday to complete fog/chip seal and scrub seal work on Egypt Central (from Billy Mayor to just past Luther Road), Oak Road, Memphis Arlington (Highway 70 to the Fiveway) and other segments; he estimated the work could take about a week or two to finish because recent rain delayed operations.
Officials described fog/chip seal as a preservation product intended to extend the life of roads rated as 'fair' rather than replace full repaving on failing pavements. The mayor and staff contrasted fog/chip seal with reclamation and hot‑in‑place asphalt reuse: reclamation involves milling and mixing with cement for severely failed sections, while hot‑in‑place techniques (used elsewhere) superheat and reuse existing asphalt. The city said it has not widely used hot‑in‑place but retains hot‑mix in‑place contractors in its FY26 bid for patching and repairs.
Becky Bailey, Bartlett’s transportation engineer, was named as the staff member overseeing the paving preservation plan and the city said it has engaged Pavement Management Group (PMG) to re‑evaluate pavement condition using a Pavement Condition Index (PCI) and guide preservation choices.
Officials asked the public for patience during the temporary rough riding that can follow fog/chip seal and said the technique is intended to defer larger mill‑and‑repave costs on fair roads.