County staff said a consultant inspected every school and found roughly $262 million in current deficiencies, $236 million in five-year life-cycle replacements, and an estimated $1.1 billion in needs over 10 years; the county identified 'option C' as an initial bond target.
Get email alerts on the Facilities Needs topic
No spam. Unsubscribe anytime.
Kirk Vaughn, a county staff member, told the School Bond Education Committee that Woolpert inspected every school building and classroom and performed an educational adequacy assessment based on North Carolina Department of Public Instruction standards.
Vaughn summarized the consultant's findings: approximately $262 million in current deficiencies, roughly $236 million in life‑cycle replacements anticipated over the next five years, and about $1.1 billion in total needs over 10 years. "Both districts have aging facilities. Estimates $262 M in current deficiencies, and additional $236 M in life cycle replacements in the next 5 years. $ 1.1 B in total need over 10 years," Vaughn said.
Vaughn also noted county staff had established "option C" as the county's initial target for the bond, without specifying the project list attached to that option during this meeting. The committee did not vote on a bond amount or specific project list at this meeting; the session focused on assessment results and next steps for outreach and procurement of PR support.
The committee scheduled follow‑up work on public relations procurement and agreed to reconvene on Aug. 20 to continue planning.