Alburnett awards bid for grant‑assisted generator to power well 3 and fire station

City of Alburnett City Council · August 8, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council awarded the installation contract for a permanent natural‑gas generator—supported by roughly $100,000 in grant funding—to Hawkeye Electric; the generator will back up well 3 and the fire station to improve emergency resilience.

The Alburnett City Council on Aug. 8 approved a bid award for a permanent natural‑gas generator that will provide backup power to well number three and the city's fire station.

Council members reviewed two bids and noted the city had secured approximately $100,000 in grant funding to support the project; award documents in the packet show Hawkeye Electric submitted the lowest responsible bid and the council voted to accept that bid.

Staff described the project as straightforward: the generator will sit behind well 3, be tied into the existing transfer switch and electrical infrastructure, and will power both the wellhouse and the fire station in an emergency. Councilors discussed two options for gas service—bringing the line from the fire station as a private line or extending the main to the wellhouse—but said the bids did not change under either scenario.

Council approved the resolution awarding the project to Hawkeye Electric and instructed staff to coordinate installation logistics, mapping and locates so the private feed option, if chosen, will be documented and flagged in GIS records.

Officials said they hope to have the generator installed before winter but noted lead times reported by bidders ranged from four to 16 weeks, which would place installation timelines toward the end of the year depending on the contractor's lead time.