Design team narrows jail program to budget; task force raises alarms over single courtroom and loss of rapid resource center
Summary
Design-build programming compressed the new jail program to fit an approx. $205 million budget, showing ~450 beds and about 120 behavioral-health-focused beds; task force members warned the current program—which shows only one courtroom and may omit a planned rapid resource center—could create operational bottlenecks, increased transport costs and courtroom scheduling problems.
Get email alerts on the Jail Programming topic
No spam. Unsubscribe anytime.
Members of the Incarceration Prevention and Reduction Task Force on June 22 reviewed programming from the county’s design-build team and raised concerns about reductions made to fit an approximately $205 million budget.
Peter Frazier and others summarized STV’s programming work: a condensed facility footprint (from roughly 227,000 square feet to 150–155,000) to fit the budget. The program presented by the design team estimates operating capacity in the 450–460 bed range with an operational staffing plan that would support roughly 410 beds; female capacity would increase from about 57 to about 96 beds, behavioral-health-focused beds were listed at about 120, and medical detox capacity would grow from 14 to roughly 40.
Several members said those numbers come with significant tradeoffs. “It was very clear ... that nobody was happy,” Peter Frazier said, noting the project team provided a “buyback list” of items removed because of budget constraints. Arlene pressed for the inclusion of art and trauma-informed design elements, saying they are essential for staff, victims and people in custody. “Art is nourishing ... everyone who's included in this process will benefit from having art around them,” she told the task force.
Multiple members flagged two program items they said should be prioritized on any buyback list: courtroom capacity and a rapid resource center for behavioral health services. Task force members said the draft program as presented appears to include only one courtroom; several members warned that a single courtroom could become a scheduling bottleneck that lengthens pre-trial stays and drives up transport and overtime costs. Maya said losing courtroom capacity could “probably violate people's rights in terms of getting in front of a judge in a timely fashion.” Chief Corrections Deputy Caleb Erickson explained that design choices also affect the facility’s "peaking factor"—the extra capacity needed to accommodate classification and separation requirements—and said the team prioritized flexible, versatile spaces to reduce peak demand.
Staff and members outlined the near-term schedule: the validation phase was closing around the meeting date, final validation reports were expected mid‑July, operating-cost details and additional programming information were due in August, design would begin in the third quarter and construction was slated to start in 2027. Members asked that larger policy tradeoffs—such as courtroom count versus a re-entry or rapid resource center—be escalated to the executive and County Council for policy decisions.
The county’s Criminal Justice and Public Safety Committee was scheduled to receive the STV presentation the following day; IPRTF members were encouraged to attend. Task force leaders said they will forward the work-group reports and design inputs to the County Council as part of the council’s capital and operating budget review cycle.