Summary
The Planning Board approved K5 Entertainment’s amended site plan for Slick City at 150 Woodward Road, granted a variance allowing a reduced but larger-than-ordinance façade sign, and attached conditions including no live music, occupancy limits, and required improvements before a certificate of occupancy.
Get email alerts on the Land Use Development topic
No spam. Unsubscribe anytime.
The Township of Manalapan Planning Board on Dec. 11 approved amended preliminary and final site plan applications for K5 Entertainment, which will operate a Slick City family entertainment park at 150 Woodward Road within the Multi‑Sports Kingdom (MSK) facility.
The approval includes a variance for exterior signage and a series of conditions: all prior resolution conditions remain in effect, the 1,400-person maximum occupancy is unchanged, revised architectural plans and required site improvements must be completed before a Certificate of Occupancy, masonry trash enclosures must be installed, and six illuminated directional signs are permitted. The board recorded a motion to approve moved by Barry Fisher and seconded by Barry Jacobson; the vote was recorded as yes: Fisher, Castronovo, Jacobson, Kwaak, McNaboe, Hogan, Kastell, Nelson, Pollifrone; absent: Brown; not eligible: Givelekian.
Why it matters: Slick City will add a large indoor entertainment operation and scheduled programming to the existing MSK complex, with implications for local traffic, parking and neighborhood noise. The board attached operational and physical conditions intended to limit those impacts before the business may open.
K5’s principal, Andy Katz, told the board Slick City will occupy roughly 33,000 square feet and operate seven days a week with peak staffing of about 30–40 employees and off‑peak staffing of about 8–12. Reservations will be sold in 15‑minute increments and the franchise’s capacity guidance equates to roughly 330 paid guests for the Slick City portion of the building; franchise and MSK representatives said total site operations will remain under the previously approved 1,400‑person limit.
Traffic consultant Scott Kennel summarized a Nov. 19, 2025 parking and traffic analysis that counted peak demand and concluded combined peak demand from MSK and Slick City would be roughly 490 vehicles compared with 557 existing spaces on site, leaving an approximate 10% surplus.
Signage was the most contested issue. Exhibits showed illuminated channel letters and a façade element; the applicant stated the letters portion of the sign measures about 163.7 square feet and the applicant described a total blue‑background area of 392 square feet. Planner Jennifer Beahm noted that Manalapan’s sign regulations permit only 80 square feet and asked that the applicant include the blue background when calculating total area. The board discussed precedent and visibility; counsel explained the board could approve a smaller sign and that the applicant could accept or legally challenge the decision. Katz said he would proceed with installing a 120‑square‑foot façade sign.
A nearby resident, Michael Devine of 174 Woodward Road, urged the board to address noise and early morning garbage pickup, saying prior events at the structure had caused vibration and loud sound in his home. Attorney Sal Alfieri replied the applicant will not permit live bands, noting the obligation to follow the township’s noise ordinance. Mr. Klatsky said he would ask the hauler to adjust pickup times and engineer Bhaskar Halari said masonry enclosures and alternate surfacing would be explored to reduce refuse noise.
Board counsel reviewed the condition set before the vote, including the prohibition on live music and the requirement that doors remain closed to limit noise. After the board approved the amended preliminary and final site plan, counsel recorded the conditions that must be satisfied prior to issuance of a Certificate of Occupancy.
What happens next: The applicant must submit revised architectural and site plans showing the approved details, complete the required site and building improvements and satisfy engineering comments before the township will issue a Certificate of Occupancy.