County seeks extension on Grants Pass taxiway planning grant after hangar change order raises issues

Board of County Commissioners, Josephine County · April 28, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Interim Airports Manager Cherie Jadot told the board a $13,974.26 change order for a Grants Pass hangar was required because of unexpected soil excavation and backfill and noted a potential $35,000 in liquidated damages; the county will consult legal counsel and staff were directed to request a 60-day extension for a $150,000 FAA-dependent planning grant for a taxiway extension.

Interim Airports Manager Cherie Jadot told the Josephine County Board of Commissioners April 28 that a change order totaling $13,974.26 was needed on a Grants Pass Airports hangar project because unanticipated soil excavation and backfill fell outside the original contract. Jadot said she did not dispute the change order but warned the contractor could potentially owe about $35,000 in liquidated damages for project delays.

Jadot also described planning grant COAR-202203S8-00030, a $150,000 FAA-funded planning grant for a taxiway extension to Denver Avenue at the Grants Pass Airports. She said the project requires an FAA environmental assessment, which the FAA must provide, and that the county has already processed three amendments for the grant. Because the county does not expect the FAA assessment to be ready in time for another extension, Commissioner Colene Martin asked staff to seek a 60-day extension; Commissioner Gary Richardson indicated agreement and the board directed staff to request the extension.

The board did not approve the change order as a final action at the session. Instead, commissioners instructed Jadot to consult with the county’s legal department and to place the matter on a future legal counsel update agenda. The transcript does not record a contractor response or a final decision on potential liquidated damages.

Next steps: Airports staff will request the 60-day extension from the grantor and consult county legal counsel about the change order; the board will revisit the issue at a subsequent legal counsel update meeting.