Geneseo council approves $126,395 purchase of lift‑station components for Ford Road project
Summary
Geneseo approved ordering specialized lift‑station components for the Ford Road project to avoid 2–3 month vendor lead times; the council authorized a $126,395 purchase from the general fund and noted the development agreement with JF Edwards Construction Company is signed and construction has started.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Geneseo’s city council authorized the purchase of specialized lift‑station components for the Ford Road project on Tuesday, approving a $126,395 expenditure from the general fund to place an order now because vendor lead times were reported at two to three months.
City Administrator Brandon told the council the development agreement with JF Edwards Construction Company had been signed about a week to 10 days earlier and that construction has begun. He said the city has completed multiple public meetings and ordinances necessary to establish the project and the TIF and annexation steps; staff recommended ordering the components to ensure they arrive in time for a planned fall installation.
The motion to approve the purchase — described on the agenda as components specified on a price sheet from Electric Pump — was made by Council member Arnold and seconded by Rothschild (in the first session) and later reaffirmed in a subsequent session (motion by Arnold, second by Kennet). Roll-call votes in both instances were unanimous among members present.
The council recorded the expense as $126,395 to be drawn from the general fund. Staff noted the project will go to bid for construction work; ordering components now is a procurement step to mitigate long lead times, not an award of the construction contract.
Next steps: The project is slated for fall construction; staff will manage procurement timing and report back to council on contract and bid milestones.