Gilmer council approves $228,000 emergency roof replacement for Mockingbird water tank, OKs additional tank repairs
Summary
The Gilmer City Council unanimously approved an emergency $228,000 roof replacement for the Mockingbird Water Storage Tank and a $60,250 change order for additional repairs to the Ruby Street tank, citing urgent structural needs and pending refurbishment plans.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
The Gilmer City Council on Jan. 27 approved an emergency roof replacement for the Mockingbird Water Storage Tank and additional repairs to the Ruby Street tank.
City Engineer Stan Hayes told the council the Mockingbird tank required immediate roof replacement for safety and reliability; the council approved a $228,000 proposal from O&A Classic Coating to complete the work. Hayes also recommended further repairs at the Ruby Street Water Tank, and council approved a $60,250 change order for that work.
Council discussed the projects as part of broader water-system maintenance and refurbishment planning. Mary Bullock, city manager, said the city plans to cash one of its certificates of deposit to fund upcoming water-tank refurbishment work and that other investments were performing adequately.