Commission approves sewer-lining patches on Fourth Avenue to avoid street excavation
Summary
Facing root intrusion and cracked clay pipe, the commission approved a lining contract for portions of the sanitary sewer on Fourth Avenue to prevent disruptive open-cut replacement and preserve the roadway.
Get email alerts on the Sewer Infrastructure topic
No spam. Unsubscribe anytime.
The Public Utilities Commission approved a contract to install cured-in-place liner patches in clay sanitary sewer on Fourth Avenue between Fourth and Fifth streets to address root intrusion and cracking, staff said.
Staff explained crews have jet-cleaned the run twice to keep it flowing and that multiple spots show intrusion; because the street pavement is in good condition, staff recommended lining patches to avoid excavation and the higher cost of full replacement and repaving. The work was described as installing roughly 385 linear feet of 8-inch liner (the liner will reduce the internal diameter to about 7.25 inches), done as two- to four-foot patch sections to stabilize the worst defects.
Why it matters: Staff said lining will restore pipe integrity in the problem section without requiring disruptive street excavation and repaving at this time. They noted that lining slightly reduces diameter but in this run the change will not impair flow given the available capacity and slope.
Contract and cost: Staff presented bids from several firms (Vision/Visu Sewer and Hydro Clean were discussed); the meeting recorded a proposal amount of $30,250 for the lining work. The commission moved and approved the proposal.
What happens next: Staff will schedule the lining work this construction season and continue televising/jetting other town blocks as budgeted to prioritize future lining or replacement work.