Commissioners sign bids and settlement, hear updates on paving and bridge closures
Summary
Dubois County commissioners accepted bid forms for six paving contracts, signed a settlement with CenterPoint Energy over property on SR 162, and received timelines for multiple bridge repairs and closures starting in May and June 2026.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
The Dubois County Commissioners on May 18 accepted previously awarded bids for six paving contracts and signed a damage settlement with CenterPoint Energy related to 11.613 acres on State Road 162.
Highway Engineer Levi Leffert presented Bid Form 96 to formally accept awards for projects 26-02 (CalCar Paving), 26-03 (C&R Construction), 26-04 (CalCar Paving), 26-05 (CalCar Paving), 26-06 (JH Rudolph) and 26-07 (C&R Construction). The board signed the forms, completing the formal acceptance of those contracts.
Leffert also updated the board on multiple bridge projects: Blankenberger Brothers, Inc. is on schedule to pour the rigid deck overlay for Bridge 78 (CR 600 W over the Patoka River), with contractor work and curing expected before approach and guardrail work; the bridge will remain closed to through traffic during construction. Concrete overlays were scheduled this week for Bridges 107 and 240, with openings expected in early June, while Small Structure #16 was closed May 6 for beam and deck replacement with reopening anticipated within two weeks. Bridge 36 (Celestine Road N) is planned to close around June 1 for a roughly five-week deck replacement.
Highway Superintendent Donnie Lueken said chip-seal patching is planned to start the week of June 1, with patches taking approximately three to four weeks followed by overlays that could last about a month.
The board voted to approve signing the CenterPoint settlement; Commissioner Blessinger signed the document and Auditor Sandra L. Morton attested the signature. The board also discussed right-of-way concerns including keeping yard signs off the road rights-of-way and a policy allowing the Highway Department to pick up signs placed in the right-of-way and hold them for two weeks before disposal.
Leffert noted Crossvine Solar has submitted revised bore/cut permit applications for utilities in the 500W right-of-way and proposed daily road closures of roughly two weeks from 7 a.m. to 7 p.m.; the board discussed safety and closure logistics and asked staff to review concerns.