Perryton ISD approves $123,562 deductive change order with Husmann Builders
Summary
Trustees approved a change order removing a planned Michigan Street parking strip from the field-house project, reducing the project budget by $123,562; Husmann Builders attended to answer questions and no trustee opposed the measure.
Get email alerts on the Construction Contracts topic
No spam. Unsubscribe anytime.
Perryton Independent School District trustees voted unanimously to approve a deductive change order with Husmann Builders that removes a planned parking strip along Michigan Street from the field-house project, lowering the project budget by $123,562.
A district staff member explained the board had previously budgeted for the strip and then requested a change order to take the parking work out of the field-house scope. The staff member said Husmann delivered the change order and was present at the meeting to answer questions. “He is also here this morning if you guys have any questions,” the staff member said when the proposed deduct was introduced.
A trustee moved to approve the change order and another trustee seconded; the motion carried 7-0. No further discussion or public comment was recorded.
The action reduces work in the field-house contract and frees the previously budgeted funds for other uses. Trustees did not specify a new use for the $123,562 in the meeting record; that amount was described as a deduct from the approved field-house budget.