Council approves 201 Front Street mixed-use project; applicants to fund 100% affordable nearby development, heritage trees to be removed
Summary
Council approved the 201 Front Street mixed-use development using the Downtown Density Bonus, pairing it with a separately approved 102-unit 100%-affordable project at 407 Pacific to fulfill inclusionary requirements; the project requires removal of heritage street trees in the public right-of-way and includes added conditions and a voluntary $250,000 infrastructure contribution.
Get email alerts on the Land Use topic
No spam. Unsubscribe anytime.
The Santa Cruz City Council approved a major downtown mixed-use development at 201 Front Street, accepting a Planning Commission recommendation and a staff package of conditions that tie the market-rate project to a separately approved 100%-affordable development at 407 Pacific Avenue.
Planning staff described the project as demolition of the existing commercial building to permit an eight-story mixed-use building (limited to a top-plate height of 85 feet under the Downtown Plan) with roughly 245 residential units above ground-floor retail, live-work units along Laurel Street, and one level of underground parking. The proposal uses the city's Downtown Density Bonus framework and seeks a combination approach for inclusionary requirements.
The applicant told council it had partnered with CRP Affordable Housing and Community Development on a separate, 102-unit, 100%-affordable building at 407 Pacific; that project was previously approved by the Planning Commission. Under the agreement, the developer of 201 Front Street will provide the land purchase/payment framework to allow the 407 Pacific project to proceed and the city and the applicant will record a project-specific affordable housing development agreement to document timing and contingencies.
Planning staff added three project conditions (a requirement to incorporate art on the Front Street elevation to improve a largely back-of-house frontage; a long-term exterior maintenance requirement; and a South-of-Laurel Downtown-Plan requirement that a Planning Commission subcommittee review final exterior materials during plan check).
Trees and right-of-way changes: Public works and planning staff noted the frontage work will reconfigure curb, sidewalk and bike-lane geometry consistent with approved Downtown Plan cross-sections. That change places several existing public heritage street trees within new bike-lane or curb areas. Staff concluded the public improvements and required right-of-way geometry make preserving several Laurel/Pacific heritage trees infeasible; the council's approval included the required heritage-tree removal permit. At the meeting several members of the public urged preservation of the Chinese flame trees and magnolias on the site's frontages; council directed staff to verify whether any design revisions could preserve trees but staff advised the cross-section geometry limits options.
Financial contribution and amenities: The applicant committed a voluntary $250,000 contribution (initially offered at $100,000 and increased during the hearing) toward public infrastructure improvements in the area; the council incorporated that increase into the project conditions. The council also added a condition to address Front Street frontage art.
Vote and conditions: Council voted to approve the demolition, coastal permit, design permit, administrative live-work permit, heritage-tree removals, and the downtown density-bonus request subject to the Planning Commission conditions plus the three added staff conditions and the applicant's $250,000 public-infrastructure contribution. The motion passed by roll call with the members present (a councilmember recusal was noted earlier in the meeting for unrelated items). Staff will prepare the project-specific affordable housing agreement and coordinate monitoring and funding holds in case timing of the two interdependent projects diverges.
What to watch: The project will proceed through plan check and building-permit phases. The affordable-housing agreement for 407 Pacific will define money-holding arrangements if the timing of that project and 201 Front diverge. Staff said an updated infrastructure-nexus study and final permitting details will be returned to council as required.
Key quote from the applicant: "Yes, we're agreeable to an additional $150,000," the applicant representative said when asked by council to increase the voluntary infrastructure contribution to $250,000.
Local impact: The approval is the first major Downtown Plan expansion application to reach council and is part of a broader effort to increase housing capacity in the South-of-Laurel area while capping heights in line with the approved Downtown Plan.