District updates board on summer construction, bond projects and site work
Summary
Operations staff reported progress on summer construction across EMS ISD including Wayside Middle, Dick & Heidi Elkins Agriculture Science Complex, Saginaw High School additions, Fleet Wooldridge Elementary earthwork, and other bond projects; trustees asked scheduling and access questions and were shown timelines through 2027–2030 for several projects.
Get email alerts on the Facilities Construction topic
No spam. Unsubscribe anytime.
Operations leaders delivered a comprehensive update on summer construction and bond projects across the Eagle Mountain‑Saginaw Independent School District.
Hunter Lee and Aaron Hardesty detailed active work at Wayside Middle School (drive/fire lane, parking, sequencing for football field/track/tennis), progress at the Dick and Heidi Elkins Agriculture Science Complex (structure and roofing largely in place; interior MEP work underway), Saginaw High School additions (freshman locker rooms, ag/science and scene shop foundations and piers with roughly 150 of 276 piers drilled), Fleet Wooldridge Elementary (44,000 cu yd removed toward a 144,000 cu yd target with trucks hauling spoils to a nearby data center area), and Watson building renovations (demolition complete, interior finishes beginning). Presenters showed photos of site conditions, explained causes for concrete settling at the stadium entry (tree removal and moisture changes were characterized as a likely factor), and described staging to avoid hindering spectator access during the season.
Presenters also summarized bond project timelines: Saginaw Elementary estimated June 2027–June 2029 and a campus identified as 'Newcom' expected April 2028–June 2030. Trustees asked detailed logistics questions about construction access, timing of flat work for stadium entries and pier counts; operations staff confirmed front‑entry flatwork would be completed in advance of scheduled events and that efforts were ongoing to minimize disruption. The board received the update and thanked staff for the information.