Redevelopment board approves change order, roundabout payment and bond requisitions

Hobart City Redevelopment Authority Meeting · March 16, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved change order #9 for the Colorado tracking project (about $6,688), authorized a partial roundabout payment of $253,350, and approved bond requisitions (76 and 77) and the register of claims totaling about $280,409.46.

The Hobart Redevelopment Authority approved a set of infrastructure payments and contract actions, including a change order for the Colorado tracking project, a partial roundabout payment and two bond requisitions.

Change order: Speaker 3 presented change order number 9, explaining the work is required so electricity connections can reach a junction box following a utility pole relocation. He told the board the item totals roughly $6,688.02 and that, despite the change order, the project remained “about $64,000 under budget,” meaning the RDC would not incur additional net costs at this time. The board moved, seconded and approved payment for change order #9.

Roundabout payment: The board reviewed a partial payment application for the roundabout project. Speaker 3 said crews had completed most of the work with only minor items outstanding; the payment discussed and approved at the meeting was $253,350.

Bond requisitions and claims: The board considered bond requisitions tied to lease-rental bond projects (requisition 76 and requisition 77) and approved both, recording motions and seconds. Staff also presented the register of claims and invoices—amounting to about $280,409.46—for RDC approval; the board voted to approve the register.

Why it matters: These approvals keep multiple capital projects moving and authorize payments necessary for contractor progress while staff monitors remaining punch-list items and overall project budgets.

Next steps: Staff will continue contract administration and return to the board with any subsequent change orders or outstanding invoices that materially change project budgets.