City staff say Schainker Plaza punch-list items resolved ahead of reinspection; ice ribbon work set for fall

Ames City Council · June 9, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff reported progress on Schainker Plaza corrective items, said the state reinspection was scheduled and that the contractor will replace a damaged walkway and undersized bike pads; the ice ribbon removal/replacement is scheduled September–November and the plaza may open after reinspection.

Parks/facilities staff told the Ames City Council that most remaining punch-list items at Schainker Plaza have been corrected and a state reinspection was scheduled for the afternoon following the meeting.

Staff reported corrections to spray-pad pump interlocks, recirculation rate adjustments, and pipe labeling; contractor Henkel will replace a damaged walkway near the food-truck area and will correct undersized bicycle concrete pads at no additional cost to the city. The ice ribbon replacement schedule submitted by Henkel shows removal beginning Sept. 1 with completion by Nov. 13, and the fence around the plaza perimeter was scheduled for removal after the reinspection and licensure.

Staff said a press release would be prepared after the reinspection confirms acceptance and that the city plans to open the plaza once state approval is obtained.