City hears Bolton & Menk update on water treatment project and DNR wastewater compliance
Summary
Bolton & Menk engineer Katie Sterk updated the Britt City Council on the water treatment plant project and explained the Iowa DNR wastewater compliance schedule; the council asked questions but took no formal action on selecting engineers.
Get email alerts on the Infrastructure Water topic
No spam. Unsubscribe anytime.
Katie Sterk, an engineer with Bolton & Menk, presented a progress update on Britt’s water treatment plant project and outlined a proposed approach for the city’s future wastewater treatment work.
Sterk described the Iowa Department of Natural Resources (DNR) compliance schedule for wastewater and walked council members through the firm’s plan should Bolton & Menk be chosen as engineers for a future sewer treatment plant. According to the minutes, Sterk also answered questions from council members about project timing and next steps but no vote or selection of engineers occurred at the meeting.
Council members did not take formal action on the engineer selection or contract at this session. The presentation was recorded as an informational update; staff or the council will need to return the item to a future agenda if they wish to move toward an engineering contract or formal selection process.
The update is part of ongoing planning for the city’s water and wastewater infrastructure; the council’s next steps were not specified in the minutes.