Atkins council approves $451,687 pay application; fire station project 76% complete
Summary
Council approved pay application No. 10 to Garland Construction for $451,687 and heard a progress update showing the fire station contract at approximately 76% complete; retainage and remaining balance figures were presented by city staff.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
City Administrator Scott updated the Atkins City Council on the fire station construction and presented pay application No. 10 from Garland Construction covering October work.
Scott said the original contract sum is $3,376,000 and that change orders to date have been small (net less than $6,000). He reported the current pay estimate for approval was $451,687, retainage at 5% ($127,188), and the balance to finish listed in the packet (including retainage) at approximately $927,388. Scott said the project is about 76% complete and that the schedule expects contract completion near the end of January 2026, possibly a few weeks early.
Councilor Trevor Derski moved to approve pay estimate No. 10; Bob Stolen seconded. The council approved the payment by roll-call (4-0).