Subdivision for proposed event center approved conditionally; sewer easement and solar‑lease restriction required
Summary
The board conditionally approved subdivision of a roughly 160‑acre Gettysburg Land & Cattle parcel into an event‑center commercial lot and a residence, requiring easement documentation for sewer service from an adjacent parcel and a clause barring solar‑farm permits until land‑development approval is filed.
Get email alerts on the Gettysburg Subdivision topic
No spam. Unsubscribe anytime.
Salem Township supervisors gave conditional approval Aug. 21 to subdivide roughly 160 acres owned by Gettysburg Land & Cattle Company, Inc. into a commercial lot intended for an event center and a remaining single‑family residential lot.
The approval is expressly conditional: the recorded plan must be revised to correct the owner’s address, add a statement of purpose referencing the proposed event center, show pre‑ and post‑acreage figures, add specified setback lines, and include a revision number and date. The minutes require the owners to create and record a permanent sanitary‑sewer easement over an adjacent parcel owned by Robert W. Schlemmer Jr. and Judith G. Schlemmer so Lot 1 can be serviced. The certification of title and owner signatures must be revised to confirm the easement.
The minutes also reference an existing approximately 40‑acre solar‑farm lease along Bowman Road (Instrument No. 202403250006959) and add a plan note that no permits for the solar farm may be issued until a land‑development application is filed and approved. Solicitor Falatovich clarified that the board’s vote approved the subdivision only and that “a separate application will need to be submitted for the Land Development for the development of the event center.”
What happens next: Gettysburg Land & Cattle must submit the revised plan and obtain signatures and required agency approvals (SEO and DEP where indicated) before land‑development permits may be released. The township will not authorize construction permits for the event center or the solar farm based solely on this subdivision approval.