Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Infrastructure topic

No spam. Unsubscribe anytime.

Sabula staff: rip-rap off the table; levee repair will need more sand and may take longer

Sabula City Council · September 3, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Public works staff told the Sabula council that rip-rap is no longer feasible for the south levee repair and that the work will need more than the budgeted 200 cubic yards of sand; using Army Corps-provided sand could reduce cost but extend the repair timeline.

City staff updated the Sabula City Council on repairs to the south levee and said the plan has shifted away from rip-rap to a sand-based repair that will require more material than budgeted.

Travis Woodhurst told the council the repair will use more sand than the allotted 200 cubic yards. "Rip Rap is no longer an option," the minutes record. Woodhurst said the U.S. Army Corps of Engineers can provide free sand, but relying on that source will extend the repair schedule.

Council members discussed trade-offs between cost and schedule; no formal vote was recorded on design or procurement at the Sept. 3 meeting. The city will need to reconcile the added material need with available funds or accept a longer timeline if it uses Corps-provided sand.