Authority moves forward with bids for 38th Place stormwater project; phases 1–2 estimated at $5.3M

Hobart City Redevelopment Authority Meeting · March 24, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved advertising plans and accepting bids for phases 1 and 2 of the 38th Place/Fillmore stormwater improvement project; engineers estimated phases 1 and 2 cost about $5.3 million including a 15% contingency, with bids scheduled to open in May.

Staff (S2) summarized plans and specifications for the 38th Place/Fillmore stormwater improvement project and recommended moving phases 1 and 2 to bid. Staff said DNR permits are in place pending right-of-entry easements and that the project will be solicited with a pre-bid conference on April 30, bids opening May 7 and award scheduled for the May 12 meeting.

An engineer (S7) reported an updated estimate for phases 1 and 2 of about $5.3 million including a 15% contingency. Board members discussed whether to bid phases concurrently with the County Line culvert project to capture economies of scale; staff said the County Line project would have a shorter bid window and could be awarded earlier.

The board approved advertising and issuing bid documents for phases 1 and 2 by motion and voice vote. Staff will publish ads and proceed with pre-bid coordination and easement acquisition. The board did not commit final construction funding beyond the project estimate; award will occur after bid opening and formal board action.