After staff and chamber raised safety concerns for larger crowds, the council authorized up to $15,000 to rent barricades and staff a pilot safety deployment for the July 4 parade; members highlighted parking, setup time and business impacts and asked administration to return with logistics.
Get email alerts on the Public Safety topic
No spam. Unsubscribe anytime.
The Enumclaw City Council amended and approved a funding motion May 26 to allocate up to $15,000 for a trial parade safety deployment for the July 4 parade. The amendment narrowed a prior $30,000 ask (for two parades) to fund a single, one-time July 4 deployment and passed 5–1.
Council member Martineau explained the request followed a multi‑party meeting with Enumclaw Police, event planning staff and the Chamber and reflected concerns about parade crowd sizes during America’s 250th celebrations. “The request is for funding of safety of $15,000 per parade, which includes $8,000 to go towards temporary barriers,” Martineau said, noting the remainder would cover additional staffing to supervise staging and the route.
Staff described rental logistics: initial quotes for aluminum barricades covered about 4,000 linear feet (2,000 feet per side of Cole Street), setup and takedown would likely be a 3–4 day operation for the contractor, and city staff would have to handle on-site movement when appropriate. Staff reported they obtained government pricing that roughly halved initial vendor estimates but cautioned that deployed barricades could displace parking and require coordination with businesses.
Councilors debated alternatives including targeted barricades at high-risk intersections, lighter-weight plastic panels for easier city deployment, and increased staffing instead of full-route fencing. Concerns included loss of business parking, overnight street closures for deployment, and overtime costs if barricade erection must happen outside normal hours.
The council adopted an amendment to make the funding a one‑parade trial limited to July 4 and directed administration, EPD and the Chamber of Commerce to determine the safest and most logistically feasible mix of barricades and staffing. The motion passed with a recorded margin of 5 in favor and 1 opposed. Staff said they will perform logistical planning and return to council with implementation details and cost reconciliation after the trial.
The appropriation is for a one-time pilot for July 4; additional funding for December or other events would require separate council action.