Gas & Light reports microgrid tuning, federal/state resiliency grant and a review of the gas‑service moratorium
Summary
The Gas & Light liaison said microgrid equipment was delivered and commissioning is underway; the utility received MassCEC/DOE funding for resilient underground cables and is reviewing whether to extend or tighten a moratorium on certain new gas services.
Get email alerts on the Utility Infrastructure topic
No spam. Unsubscribe anytime.
Lilly, the Gas & Light liaison to the committee, updated members on multiple utility projects and policy reviews. She said two pad‑mount switches were delivered May 26 and the microgrid at the high school is being tuned and will come online soon; she noted the utility received an award from APPA for the energy park project.
Lilly also reported a MassCEC and Department of Energy grant to fund resilient underground cabling at the BB substation on Nahant Street, with construction expected to begin between June and July. Separately, the utility is reviewing its existing moratorium on certain new gas hookups — the committee discussed which residential or commercial situations might be exempt and how street‑paving timing constrains when new lines can be installed.
No formal vote was taken. The Gas & Light liaison said details on timing for construction and the moratorium review will be provided as they become available.