Plainfield approves $2.66/sq yd seal-coat contract and reprioritizes 2025 street work
Summary
Maintenance Superintendent Brice Dietz presented the 2025 street maintenance plan; the council approved Blacktop Service Co.'s single seal-coat proposal at $2.66 per square yard and agreed to prioritize 4th Street while deferring previously missed streets.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
Plainfield’s city council on Jan. 13 approved a 2025 street maintenance proposal and authorized a single-seal-coat contract with Blacktop Service Co. at $2.66 per square yard.
Maintenance Superintendent Brice Dietz reviewed the street maintenance plan, saying the city will adjust the 2025 calendar to prioritize work on 4th Street and move previously missed streets into next year’s schedule. Council Member Clyde Balvanz moved approval of the Blacktop Service Co. proposal; Council Member Chad Shurtleff seconded the motion, which passed on a unanimous voice vote recorded as "Ayes: All." The council also voted to accept monthly department reports.
The contract approval sets a per-square-yard price of $2.66 for a single seal coat; the transcript does not specify the total contract area or overall dollar amount. Implementation and scheduling details will be handled by the maintenance department, which presented the plan to the council.