Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Change Orders topic
No spam. Unsubscribe anytime.
School Building Committee approves $106,897.63 in change orders for Sherman School project
Summary
On Feb. 27, 2026, the Town of Sherman School Building Committee approved six change orders totaling $106,897.63 for the Sherman School construction project, citing drywall replacement for pre-existing water damage and other site adjustments; the motion was moved by Kerry Merkel and seconded by Matt Vogt.
Get email alerts on the Change Orders topic
No spam. Unsubscribe anytime.
The Town of Sherman School Building Committee on Feb. 27 approved six change orders for the Sherman School construction project totaling $106,897.63.
Benjamin Chasse, assistant project manager for Newfield, presented a change order log showing the six items and the total. The largest single item was a $93,246.26 change order for drywall replacement and removal in the renovation wing; Board of Education member Tim Laughlin said that work was required because of pre-existing water damage and related mold. Other items included a $6,541.85 change for the fire service main location, a $6,167.13 credit for removing a redundant cafeteria ceiling fan, a $4,715.98 revision to the electrical room to accommodate different slab elevations, ground heater rental and on-site water storage (covered by the construction management contingency), and $8,560.67 for additional rock removal beyond the original allowance.
Chair Kerry Merkel moved to approve potential change orders 18, 14R, 19, 20, 21 and 22 in the total amount of $106,897.63; the motion was seconded by Matt Vogt and the committee voted “All in favor.” The minutes record the vote as unanimous but do not list individual roll-call votes.
The committee did not record additional debate or amendments to the change orders during the meeting. The meeting then proceeded to new business and was adjourned at 12:22 PM.
