Bozrah reviews $3.3M estimate for Route 82 water project and DWSRF funding options

Bozrah Board of Selectmen · June 16, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

First Selectman Glenn Pianka presented estimated costs for the Route 82 Water Supply Project and the board reviewed Drinking Water State Revolving Fund (DWSRF) eligibility and contingencies, including a preliminary construction estimate of about $3.32 million.

First Selectman Glenn Pianka told the Bozrah Board of Selectmen on June 16 that the town has an updated preliminary opinion of construction costs for the Route 82 Water Supply Project and is pursuing Drinking Water State Revolving Fund (DWSRF) financing options. Pianka presented a cost table showing a preliminary construction estimate of $3,321,067.75 and a Town–Norwich loan-agreement project cost figure of $3,900,000.

The DWSRF summary included line items: water main construction ($2,084,500), water service construction ($540,850), miscellaneous items ($262,535), and contingencies. The table notes DWSRF-eligible portions covering roughly 75% of certain construction costs, with specified legal and contingency costs listed as 100% the town must account for. Pianka said the materials were provided to the board as an attachment for review.

Why it matters: the Route 82 project is capital-intensive and will require coordination with Norwich utilities and DWSRF rules, including bid-package preparation, construction administration, inspection, and possible ineligible items the town must fund. The cost table assigns the town responsibilities for bid-package preparation, construction administration, preparation of as-built plans and any items deemed ineligible for DWSRF reimbursement.

Board members did not take a final vote on the project at the meeting; Pianka presented the estimates for consideration and next steps. The document provided shows contingency line items (DWSRF contingency and a Norwich contingency) and a note that the preliminary opinion of construction costs is in 2026 dollars.

The board is expected to consider next procedural steps, including financing arrangements or additional public hearings, as the project moves from conceptual estimate toward formal procurement and construction planning.