Engineer details Depot Street bridge replacement; commissioners to seek detour funding

St. Clair County Commission (work session) · June 18, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County engineer briefed commissioners on a Depot Street bridge replacement that includes a federal direct appropriation and a local match; commissioners were told federal funds cannot pay detour upgrades and agreed to seek state help for detour improvements and to provide design needs to request funding.

County Engineer Clay Phillips walked the commission through plans and a funding breakdown for the Depot Street (Riverside) bridge replacement, including a federal direct appropriation and a local match that leaves the county responsible for certain costs such as the detour.

Phillips said the bridge project will be let to bid Sept. 30 and that a standard construction timeframe for a cast-in-place bridge of the discussed size could reach up to about 120 calendar days. Commissioners and staff noted that federal and state project funds cannot be used for detour upgrades; the county will likely have to fund or obtain separate state assistance to upgrade an existing alternative route to serve as a detour during construction.

Commissioners cited an earlier trip to Washington, D.C., and described a direct appropriation the group obtained; during the discussion the chair referenced a "million-dollar direct appropriation" tied to that effort and asked Phillips to draw up exact detour-cost figures so the commission could pursue state representatives for additional funding. A local-share figure of approximately $255,000 was discussed as the county portion to meet required matches.

The commission asked the engineer to develop cost estimates for improving the detour route and to provide drawings and cost breakdowns for use in budget planning and state outreach.

Next steps: engineering staff will prepare detour upgrade estimates and construction schedules for commissioners to use when requesting supplemental state funding and finalizing the local match.